CAAB faces mounting pressure as HSIA T3 loan repayments begin


Dhaka
: The Civil Aviation Authority of Bangladesh (CAAB) is preparing for a major
financial challenge as repayments for the loans used to build Dhaka Airport's
Third Terminal are set to begin in June, even though the facility is unlikely
to start generating income before 2027.
Under
the repayment schedule for a Japanese loan worth nearly BDT 17,000 crore, CAAB
is expected to pay around BDT 1,200 crore in June and another BDT 1,000 crore
in December this year. Officials said, as per reports, the first year's
repayment burden alone could absorb almost all of the organization's annual
profits.
CAAB
had earlier managed to delay the repayments by three years after the original
schedule targeted 2023. However, with the grace period ending, the authority
must now start making payments regardless of whether the terminal becomes
operational.
Officials
within the aviation sector fear the repayments could strain CAAB's finances and
affect airport operations and development projects across the country. Concerns
have also emerged over whether the authority may need to use its reserves to
continue routine maintenance, safety improvements, and procurement of critical
airport equipment.
The
delay in launching the Third Terminal has largely been linked to unresolved
negotiations over management and revenue-sharing arrangements with a Japanese
consortium. The consortium includes Japan Airport Terminal Company, Sumitomo
Corporation, Nippon Koei, and Narita International Airport Corporation.
Although
the terminal is almost complete, disagreements over operational control
prevented it from meeting its planned launch target in 2024. According to CAAB
officials, negotiations slowed considerably during the tenure of the interim
administration before discussions resumed earlier this year.
Aviation
analysts argued, the delays have created unnecessary financial pressure.
Industry insiders said, CAAB should have finalized an agreement immediately
after construction was completed so that operational income from the terminal
could help offset loan repayments.
Even
after an agreement is signed, the terminal is unlikely to open immediately.
CAAB Chairman Air Vice Marshal Md Mostafa Mahmood Siddiq recently said it could
take several months to complete negotiations, followed by a lengthy operational
testing phase known as ORAT (Operation Readiness and Airport Transfer). As a
result, the terminal may not become fully operational until 2027.






