HSIA's third terminal set for partial opening on December 16


Dhaka
: The third terminal of Hazrat Shahjalal International Airport in Dhaka is
scheduled to begin limited operations on December 16, with an initial four
flights, as authorities race to complete the remaining preparations and
finalize an operating agreement with a Japanese consortium.
Civil
Aviation and Tourism Minister M Rashiduzza-man Millat announced the plan at a
preparatory meeting at the Civil Aviation Authority of Bangladesh (CAAB)
headquarters on November 14. The initial operation will cover two arriving and
two departing flights, with services expected to increase gradually.
Millat
said opening the terminal was an important commitment of the government and
urged all relevant agencies to complete their assigned tasks within the
deadline, giving priority to the prime minister's directive.
The
meeting reviewed preparations involving immigration booths, baggage belts and
scanners, trial operations, and the signing of necessary agreements.
Representatives of the agencies concerned discussed progress and outstanding
work.
Meanwhile,
the CAAB board approved the draft concession agreement with a Japanese
consortium at a meeting on November 10. The draft is expected to be sent to the
Ministry of Civil Aviation and Tourism for further scrutiny and approval before
proceeding through the relevant government channels.
The
consortium comprises Japan Airport Terminal Co Ltd, Sumitomo Corporation,
Nippon Koei and Narita International Airport Corporation. The proposed
agreement covers operation of the terminal and ground-handling services.
The
draft has drawn attention over several contractual provisions, including
ground-handling responsibilities, revenue sharing, legal protections and
liability for construction defects. A proposed restriction on competing
civilian airports beginning commercial operations within 100 kilometers of
Dhaka airport for 15 years has also attracted scrutiny. The final terms remain
subject to further review.
The
terminal, built with financing from the Japan International Cooperation Agency,
was ceremonially inaugurated in October 2023 but has yet to handle regular
commercial flights.